Vedadots
Q1920/80Q21
Q20·CSAT · Prelims 2023

Alternating time and work schedule (A, B, C)

NumericalTime & WorkArithmetic word problemMedium

Question

A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements:

1The work will be finished on Thursday.
2The work will be finished in 10 days.

Which of the above statements is/are correct?

Options

a

1 only

b

2 only

Answer
c

Both 1 and 2

d

Neither 1 nor 2

Explanation

Determine total work by finding the LCM of individual timelines: LCM(8, 16, 12) = 48 units . Compute individual daily output rates: A = 48 / 8 = 6 units/day B = 48 / 16 = 3 units/day C = 48 / 12 = 4 units/day

They work in a strict rotational cycle: Day 1 (A), Day 2 (B), Day 3 (C). Output per 3-day cycle = 6 + 3 + 4 = 13 units.

Track progress cycle by cycle:

3 cycles (9 days) consume: 13 × 3 = 39 units.
Remaining work = 48 - 39 = 9 units.

Now map out the 4th cycle starting on Day 10:

Day 10 (Turn goes to A): A can complete 6 units. Total units reached = 39 + 6 = 45. Remaining work = 9 - 6 = 3 units.
Day 11 (Turn goes to B): B can do 3 units per day, which perfectly clears the remaining 3 units.

The work finishes exactly at the end of Day 11. Let's check the week-day map starting on Monday: Day 10 is Wednesday, and Day 11 is Thursday. Thus, Statement 1 is Correct. Total days required is 11, making Statement 2 Incorrect.

Self-Correction Check on Option mapping: Statement 1 says "finished on Thursday", which matches our day-of-week calculation. Statement 2 says "finished in 10 days", which is false. Thus, only Statement 1 is correct.

In cyclical workforce rotations, calculate the grouped output per block first, use integer division to fast-forward through complete cycles, and track the final remainder manually step by step.

Answer: (a).

Question details

Year

2023

Paper

CSAT

Question

Q20

Section

Numerical Ability

Sub-topic

Time & Work

Type

Arithmetic word problem

Difficulty

Medium

Source hint

Time-work application

Same sub-topic — other years

Time & Work has appeared in multiple CSAT papers:

See all questions on Time & Work

Browse every tagged question across all years

Explore →